Module 05 Activity – Review a Project Schedule and Evaluate for Potential Issues/Cost Impacts

In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.

Activity
Task
Predecessors
Duration
Activity CostASign ContractNone5 days$5,000BDesign SurveyA3 days$1,500CIdentify AudienceA7 days$1,000DRun SurveyB, C30 days$6,000EAnalyze ResultsD5 days$3,000FCreate PresentationE5 days$1,000GPresent to ClientE, F2 days$3,000

Connect with a professional writer in 5 simple steps

Please provide as many details about your writing struggle as possible

Academic level of your paper

Type of Paper

When is it due?

How many pages is this assigment?

  • Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module’s lecture.
  • What is the duration of the project?
  • How much slack is currently available in the non-critical path?
  • How long are the project and feeder buffers?

 

“Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!”

The post Module 05 Activity – Review a Project Schedule and Evaluate for Potential Issues/Cost Impacts appeared first on Graduate Paper Help.

Looking for a Similar Assignment? Let us take care of your classwork while you enjoy your free time! All papers are written from scratch and are 100% Original.